Timeline for Service Requests

When to submit applications and complete customer requirements

Job types for residential and commercial customers Job type example(s) Please contact us PPL employee will contact you to review the scope of your request Customer requirements to be completed, excluding electrical inspections and trenching Final customer requirements, if applicable
Interruptions to existing service Customer needs power shut off temporarily for tree trimming around a wire, or to install a new meter base Minimum of 6 weeks before your planned work Within 5 business days N/A For meter base change, present or submit inspection card the day of, or prior to the day of reconnect
Installation of electric service Customer is building a new house, apartments or business
Minimum of 12 weeks before your planned work
Within 5 business days
6 weeks prior to your scheduled work date
Service trench and electrical inspection 2 weeks prior to your scheduled date
Line extensions
Customers need to extend a power line – either underground or overhead – to a new home, shed, etc.
Minimum of 12 weeks before your planned work
Within 5 business days
6 weeks prior to your scheduled work date
Service trench and electrical inspection 2 weeks prior
Upgrades in service
Homeowner is building a large addition, requiring upgrade from 100-amp service to 200-amp service
Minimum of 12 weeks before your planned work
Within 5 business days
6 weeks prior to your scheduled work date
Service trench and electrical inspection 2 weeks prior
Residential Service Relocations
Customer is moving a driveway, resulting in the need to move utility poles or PPL wires
Minimum of 12 weeks before your planned work
Within 5 business days 6 weeks prior to your scheduled work date
Service trench and electrical inspection (if required) 2 weeks prior
Underground Residential Developments (URDs)
PPL needs to install service to a new/expanded residential development
Minimum of 1 year before your planned work
Within 5 business days
6 weeks prior to your scheduled work date
Primary trench 1 week prior
Street Lights and area lights
Township, Homeowners Association, etc. would like a new street or area light
Minimum of 6 months before your planned work
Within 5 business days
6 weeks prior to your scheduled work date
N/A