Report Emergency
Skip to main content
Español
Account Summary
Make a Payment
View Bills & Payments
Check Usage
Outages and Issues
Start/Stop/Move Service
Sign In
Settings
Contact Us
More
One-line Display Standards
PPL Electric Utilities requires the following included in the customer one-line drawing, where applicable:
Lightning Arrestors (LA's)
Primary equipment on the Transformer (example: CB's, disconnects, circuit switches)
Potential Transformers (PT's) and Current Transformers (CT’s)
Customer Transformer data (kVA for 12kV Rating or MVA for 69kV, Delta-Wye or Wye Delta transformer winding configuration)
Customer Secondary equipment on the Transformer (example: CB's, Disconnects)
If applicable: the TIE between two sections, Customer Secondary Bus (TIE CB, and disconnects)
Customer Emergency Generation and/or Distributed Generation/Renewable
If applicable: tie on PPL EU’s 12kV Distribution System or PPL EU’s 69kV Transmission System (Alternate Supply).
What the customer designations are for all the devices as mentioned above. (Example Trans 1, Tap 1 AB, 52-4 CB, Sect 1 Bus etc.)
If there are any key interlocks with CBs or air breaks.
PPL Electric Utilities, May 14, 2024
Powered by GlobalLink Web